Location: Poznań

Implementation of the design and construction supervision of the logistics hall and plant reconstruction

The construction area – 105,000m2
In the years 2018-2020
IT infrastructure:
  • 2 network distribution rooms
  • 18,000 m of optical fibers
  • 90,000 m of copper cables
  • Full coverage of the WIFI wireless network
CCTV:

Designing a monitoring system in the area of the reconstruction as agreed with the users and the security department.

Fire alarm systems:
  • The system provides full coverage for fire protection on 105,000m2
  • Design for the fire alarm network system modernization
  • Fire control matrix for the plant
Access Control:

Designing a monitoring system in the area of reconstruction as agreed with the users and the security department.